Highview Construction Updates

100% Completion

       

94% Completion - October 08 

75% Completion - July 08 

45% Completion - Apr 08 

40% Completion - Mar 08 

Structural works is currently at 100% to level 6 Plenty Rd & Level 4 High Street.
Internal services rough in and stud framing has commenced on Level 2 Plenty Rd & Level 1 High Street.

30% Completion - 22 Jan 08 

High Street Tower
·         Structural column work has commenced on level 3
Plenty Road Tower
·         Structural slab work has commenced on level 4
·      
Level 1 set out, drains & windows installation, metal stud framing, mechanical
      & plumbing rough in & joinery measure are in progress

20% Completion - 28 Nov 07

Level 1 Slab on the Plenty Rd Tower is completed with formwork for the level 2 slab commenced. Upper Ground Level slab on the High Street Tower is completed with formwork for the level 1 slab commenced.

5% Completion - 6 Sep 07

Structural retaining wall works are in progress. Earthwork preparations are underway for the ground floor slab to be poured.