Highview Construction Updatescall now on 8602 0835
100% Completion
94% Completion - October 08
75% Completion - July 08
45% Completion - Apr 08
40% Completion - Mar 08
Structural works is currently at 100% to level 6 Plenty Rd & Level 4 High Street. Internal services rough in and stud framing has commenced on Level 2 Plenty Rd & Level 1 High Street.
30% Completion - 22 Jan 08
HighStreetTower ·Structural column work has commenced on level 3
PlentyRoadTower ·Structural slab work has commenced on level 4 ·Level 1 set out, drains & windows installation, metal stud framing, mechanical & plumbing rough in & joinery measure are in progress
20% Completion - 28 Nov 07
Level 1 Slab on the Plenty Rd Tower is completed with formwork for the level 2 slab commenced. Upper Ground Level slab on the High Street Tower is completed with formwork for the level 1 slab commenced.
5% Completion - 6 Sep 07
Structural retaining wall works are in progress. Earthwork preparations are underway for the ground floor slab to be poured.