Travancore on the Park received Certificate of Practical Completion on
21st April 2008.
99% Completed - 4 Mar 08
Practical completion has now been achieved for all apartments. Final finishing touches are currently in progress to the Piazza.
98% Completed - 22 Jan 08
Occupancy Permit was issued for Levels 2, 3 & 4 on Friday 25 January 2008.
Practical completion for the entire works is currently scheduled mid 25 February 2008.
90% Completed - 28 Nov 07
Travancore nears completion with the finishing touches being applied. Piazza takes shape with the planting of trees. Residence units are 99% completed. Officeworks has now commenced trading.
35% Completed - 21 Feb 07
The construction of the level 2 slab is in progress. Piazza slab works have commenced