Travancore Stage 1 Updates

100% Completed  -  20 Apr 08

Travancore on the Park received Certificate of Practical Completion on 21st April 2008.

99% Completed  -  4 Mar 08

Practical completion has now been achieved for all apartments. Final finishing touches are currently in progress to the Piazza.

98% Completed  -  22 Jan 08

Occupancy Permit was issued for Levels 2, 3 & 4 on Friday 25 January 2008.
Practical completion for the entire works is currently scheduled mid 25 February 2008.

90% Completed - 28 Nov 07

Travancore nears completion with the finishing touches being applied. Piazza takes shape with the planting of trees. Residence units are 99% completed.  Officeworks has now commenced trading. 

35% Completed - 21 Feb 07

The construction of the level 2 slab is in progress. Piazza slab works have commenced 